1. Perform Earned Value Analysis of the given project.(10)
The progress after the end of 12th day is as follows:
Calculate SV, SPI,CV and CPI respectively.
asked in 2078(New Course)
1. What is software project management? How software project differs from other projects?
asked in 2074
1. Outline the contents of a Software Project Management plan and explain in detail.
asked in 2075
1. Explain the important activities that a software project manager performs during software project planning.
asked in 2076
1. What is project? Explain different phases of project planning.
asked in 2070
1. Explain about software product attributes.Explain the project management cycle and SPM framework.
asked in 2077
1. Explain the software engineering problem. What do you mean by software project management? Explain.
asked in 2072
1. Explain the project management cycle. What are the five competencies of project management skills? Explain
asked in 2073
2. Differentiate between programme management and portfolio management. Define Payback period. How can it be used as an evaluation technique? What are its advantages and disadvantages?(5+2+1+2)
asked in 2078(New Course)
2. Differentiate between project life cycle. What do you mean by project planning and scheduling.
asked in 2077
3. Suppose you have been assigned to develop online voting system. List four risks that might affect the success of the system. Rank the risks based on Risk exposure. Develop contingency plan for the highest ranked risk.(2+6+2)
asked in 2078(New Course)
3. Explain the software configuration management with its roles and tasks.
asked in 2077
4. Calculate ROI for the following project.(5)
asked in 2078(New Course)
4. List out the activities used in SPM.
asked in 2074
4. Explain the SPM framework.
asked in 2075
4. Explain about SPM framework.
asked in 2076
4. What do you mean by SPM framework?
asked in 2070
4. Explain the various steps involved in stepwise project planning?
asked in 2077
4. What do you mean by SPM framework?
asked in 2072
4. What do you mean by Software Project Management? In what ways software projects are different from other types of projects?
asked in Model
5. Differentiate between activity-based approach and hybrid-based approach for identifying activities.(5)
asked in 2078(New Course)
5. Explain the process of analysis the cost benefit in project evaluation.
asked in 2077
6. Why software project management is a challenging activity?(5)
asked in 2078(New Course)
6. Explain the contents list of project plan.
asked in 2076
6. Explain the rapid application development.
asked in 2077
7. Draw precedence network diagram for the following and identify the critical path.
asked in 2078(New Course)
8. Explain Maslow's hierarchy of needs.(5)
asked in 2078(New Course)
7. What are the factors needed for allocating a task? Explain.
asked in 2077
9. Briefly explain different quality factors.(5)
asked in 2078(New Course)
8. Discuss about change control with example.
asked in 2077
9. Write the goal of software project planning.
asked in 2073
10. Explain the process of Software Configuration Management.(5)
asked in 2078(New Course)
10. What are the four major activities involved in project management? Explain.
asked in 2070
9. Explain about the selecting the right person for the job.
asked in 2077
11. Different between Gantt chant and slip chart.(5)
asked in 2078(New Course)
10. Explain the major sections of a Software Quality Assurance plan.
asked in 2077
14. Write short notes on:
a. Present worth
b. PERT chart
asked in 2078(New Course)
11. Explain the process of effort estimation using function point analysis with example.
asked in 2077
13. Write short notes on:
a. SPM software
b. Critical Path
asked in 2074
12. What are the advantages and disadvantages of COCOMO?
asked in 2077
13. Write short notes on:
(a) SQA plan
(b) SPM tools
asked in 2077
6 questions
1. What are different steps of Project Planning? Describe activities in each step.
asked in Model
asked in 2076
5. Differentiate between project life cycle and product life cycle.
asked in 2075
5. Explain the product life cycle.
asked in 2070
5. Explain the product life cycle.
asked in 2072
13. Write short notes on:
(a) Project schedule
(b) Test plan
asked in 2073
20 questions
2. Differentiate between strategic Assessment and technical assessment. Explain the steps involved in cost benefit analysis?
asked in 2074
2. Explain in the cost benefit analysis in details. Explain the evaluation techniques of cost benefits.
asked in 2070
2. What do you mean by rapid application development? Differentiate between spiral models and prototyping model.
asked in 2072
3. Explain the risk type and also explain in details how will you managing risks.
asked in 2074
3. Mention at least five examples of software development projects that would require prototyping. Explain each of them.
asked in 2073
3. Why are process Capability Models more effective than product matrices? Describe any 3 capability models in detail
asked in Model
4. Define the terms: Net profit value and pay-back period.
asked in 2073
5. Explain the use of decision tree in Risk Evaluation.
asked in 2074
5. Differentiate between rapid application development and waterfall model.
asked in 2076
5. Explain the role of cost estimation in software development project.
asked in 2073
5. Explain cost benefit evaluation techniques.
asked in Model
6. Briefly explain about risk planning and controlling.
asked in 2074
6. Comparison between waterfall model with spiral model.
asked in 2075
6. What do you mean by cash flow forecasting?
asked in 2070
6. Explain the cost-benefit evaluation techniques.
asked in 2072
7. Explain the process of collecting the data.
asked in 2074
7. Differentiate between risk planning and risk reduction.
asked in 2076
9. Mention atleast seven deliverables in a software project
asked in 2070
11. Explain the three modes of the basic COCOMO model.
asked in 2075
12. Discuss the role of cost estimation in software development project.
asked in 2070
9 questions
2. Explain in detail about critical path scheduling method with example.
asked in 2075
2. The table below is an example of project specification with estimated activity duration and precedence requirements:
Activity Name | Activity Name | Duration (Weeks) | Precedents |
A | Hardware Selection | 6 | |
B | System Configuration | 4 | |
C | Install Hardware | 3 | |
D | Data Migration | 4 | A |
E | Draft Office Procedures | 3 | B |
F | Recruit Staff | 10 | |
G | User Training | 3 | E,F |
H | Install and test system | 2 | C,D |
asked in Model
6. Why is it necessary to plan the activities?
asked in Model
7. Explain the objectives of activity planning.
asked in 2075
7. Explain the network planning model with example.
asked in 2072
8. Explain the Gantt Charts in Scheduling with example.
asked in 2075
8. Describe the major workflows involved in software development.
asked in 2076
9. How network chart help in scheduling a project?
asked in 2076
10. Explain the critical path with example.
asked in 2076
5 questions
6. Why are PERT/CPM used in software project management? Explain.
asked in 2073
7. Discuss the concept of PERT/CPM in software project management.
asked in 2070
7. What are different types of resources? How do you schedule them in the project?
asked in Model
8. What do you mean by resource allocation?
asked in 2072
13. Write short notes on:
(a) Resource allocation
(b) Earned value
asked in 2070
6 questions
8. How do you visualize progress of the project? Explain any two types.
asked in Model
9. What do you mean by change control?
asked in 2072
11. Explain the visualizing progress in details with example.
asked in 2074
11. Explain the visualizing progress in detail with practical example.
asked in 2076
11. How can we do project monitoring and control? Explain.
asked in 2070
13. Write short notes on:
a. Charge Control
b. Software Quality
asked in 2075
6 questions
8. How you can select the right person for the job? Explain.
asked in 2074
9. What are the roles of Software Engineer in a project? Explain.
asked in 2075
9. Describe the typical terms of a contract.
asked in Model
10. Explain the typical terms of contract? Mention the different types of people in the team in the software project management.
asked in 2072
10. What are the stages of Team formation model?
asked in 2073
12. What are different types of people in a team? Explain various stages a team passes through.
asked in Model
16 questions
2. What are the five maturity level of CMM? Differentiate between leaders and managers.
asked in 2073
3. Explain the various maturity levels of SEI CMM and also discuss the key process areas for each level.
asked in 2075
3. Explain the different techniques for enhancing the quality of software project.
asked in 2076
3. Explain the SEI Capability Maturity Model (CMM) and SQA plan.
asked in 2070
7. Explain the software quality factors.
asked in 2073
8. Explain the QA organizational structure.
asked in 2070
8. Explain the SEI capability maturity model (CMM).
asked in 2073
9. Define software quality and its importance.
asked in 2074
10. Describe Verification and Validation of the Program.
asked in Model
11. What do you mean by verification and validation? Explain with example.
asked in 2072
11. Explain the quality assurance plan
asked in 2073
12. Explain the SQA plan with example.
asked in 2075
12. Write short notes on:
(a) Visualizing progress
(b) Test strategies
asked in 2072
12. Explain the program verification and validation with example.
asked in 2073
13. Write short notes on:
a. SQA plan
b. SPM tools
asked in 2076
13. Write short notes on:
a.Test Plan
b. Change Control
asked in Model
6 questions
3. Explain the software configuration management and its tasks and roles.
asked in 2072
10. Explain about SCM tasks and tools.
asked in 2074
10. Explain the function of software configuration management.
asked in 2075
11. What do you mean by configuration management? Write its importance in a software project.
asked in Model
12. Explain the software configuration management and its roles.
asked in 2074
12. Explain the software configuration management with example.
asked in 2076